Cost Analysis
Authored by Mark Lorie, JHU graduate student, this document provides an analysis of the cost of implementing CAPM. The approach and the basic assumptions used in this analysis as well as the costs for implementing the system at JHU and in general are categorized and explained. Some of the risks associated with the implementation of CAPM are explored.
Mark Lorie, Graduate Student
Department of Geography and Environmental Engineering
Johns Hopkins University
Moravia Park is an off-site shelving facility for the Johns Hopkins University (JHU) Milton S. Eisenhower Library (MSEL). Moravia Park provides shelving for books that do not fit into the shelving area at the MSEL. Books that are not considered high use materials (i.e., have not been checked out in a specified amount of time) are shelved at Moravia Park. When an individual would like to look at a book shelved at Moravia Park, he or she must submit a request via fax, email, or by filling out a form on the web or at MSEL. The requested materials are then delivered to MSEL within 2 to 24 hours. The request process is similar for journal articles, although the waiting period may be less since the articles can be faxed to the user or scanned into a portable document format file and sent electronically. The implementation of CAPM will give library patrons real time access to books shelved at Moravia Park through the use of scanned images posted to a webpage.
This document provides an analysis of the cost of implementing CAPM. The next section describes the approach and the basic assumptions used in this analysis. The costs for implementing the system at JHU and in general are categorized and explained in the Section 3. Some of the risks associated with the implementation of CAPM are explored in Section 4. Finally, some brief conclusions are offered in section 5.
Approach and Basic Assumptions
This cost analysis provides information on the initial expenditures for the components that comprise the CAPM system, and expected costs for the operation and maintenance of the system. Additionally, opportunity costs associated with changes to the setup of Moravia Park will be considered (see Figure 1). The analysis presents a general framework for costs likely to be incurred in implementing the system, utilizing numbers specific to JHU. There will be some differences in the costs faced by JHU and those faced by other institutions since the development costs for the CAPM system were covered by a grant to JHU. Therefore, JHU will not face costs for some of the hardware, whereas other institutions might incur these costs. The Andrew W. Mellon Foundation awarded the grant to JHU.
Figure 1: Components of the Costs for Implementing CAPM

- Robot Costs
- Page-turner costs
- Costs of book containers
- Costs for scanners
- Computer charges
- Set up costs
- Labor
- Equipment Maintenance
- Building space due to reduced storage capacity
Each category will be described in detail below. It is important to recognize that the operating costs will be incurred annually, while fixed costs are one-time costs that will be incurred at the inception of the project, or may be paid back over a period of time. A ten-year time horizon is considered in this analysis (if this is not explained later, we should mention that this timeframe was chosen because we assume that the CAPM technology may be obsolete in 10 years).
Since the system is still under development, there are many uncertainties and some degree of flexibility with regard to the design of CAPM. Two basic operation scenarios are considered See figure 2). The first scenario (Scenario I) considers a completely automated system. Under this scenario, a robot retrieves a book from a shelf and brings it to a scanner where the appropriate pages are scanned with the help of an automated page-turner. The robot then returns the book to the shelves.
Figure 2: Scenarios Considered

There is an important uncertainty associated
with the fully automated scenario. In order to extract a single book from a
shelf, the robot will require spaces on each side of every book. Currently,
books at Moravia Park are stored in large boxes with about 10 to 20 books per
box. Two possibilities for creating the required spaces between books are considered.
One possibility (Scenario Ia) is that books will be stored in individual cartons,
such as those used for VHS videos. Each carton, slightly larger than its book,
will be stored in the larger boxes as the books themselves are in the current
system. Another possibility (Scenario Ib) is that books will be stored in large
boxes as they are now, with the spaces created by placing pieces of foam between
each book.
Under Scenario II, there is no automated
page-turner. In this case, a robot retrieves the box containing a requested
book from a shelf and brings it to a scanner. A person then scans the requested
book, replaces it in the box, and the robot returns the box to the shelf. Under
this partially automated scenario, books are stored in the boxes as they are
now (i.e., about 10 to 20 books per box and no spaces between the books).
At the initial implementation, CAPM will
operate as the partially automated system described above. However, it is the
ultimate goal of JHU to have a fully automated system, thereby maximizing the
possible benefits to library patrons. It is anticipated that the robotic page-turner
will be developed in a follow up project. Therefore, it is assumed in this analysis
that the upgrade to make CAPM a fully automated system will occur five years
after the initial implementation. Therefore, all additional costs associated
with the fully automated system will be incurred in year 5. For comparison,
the analysis also considers CAPM remaining as a partially automated system throughout
the ten-year time horizon.
Once numbers have been determined for
each cost category, a total cost for the ten year period can be determined and
presented in present worth terms (i.e., in 2001 dollars). The costs can also
be expressed as a cost per use. A cost per use number represents the levelized
costthe amount that would have to be charged per use in order to recover
all the costs over the assessed time period. There are no plans to implement
a fee per use system for CAPM; the costs per use numbers are presented for information
purposes only.
To calculate cost per use values, some
assumptions about demand for CAPM's services were made. Currently, library patrons
request 60 items per day from Moravia Park. A range of use levels centered at
the current value was used. To examine the possibility of CAPM being used less
than the current system is used; use rates of 20, 30, and 50 requests per day
were analyzed. Growth in demand was also considered by analyzing cost per use
values for request rates of 75 and 100 per day.
3. Costs to Implement CAPM
3.1 Fixed Costs
Robot: The cost of the robot is not considered
in the analysis for JHU because the development of the robot was funded by the
grant from the Mellon foundation. In general, however, the robot would have
to be purchased at the time of implementation. The estimate for the cost of
the robot is based on manufacturing additional robots, not the development costs.
The JHU Mechanical Engineering Department estimates that a robot will cost between
$50,000 and $100,000.
Page Turner: It is anticipated that the page turner
will be developed with grant support, so it will not be one of the costs associated
with JHU's implementation of CAPM. For other institutions implementing CAPM,
the cost of the page-turner is estimated by the JHU Mechanical Engineering Department
to be between $5,000 and $50,000. This range represents possible costs for manufacturing
additional page turners.
Scanner: For Scenario I, only one scanner will
be used. The initial cost of that scanner is not considered in the analysis
for JHU because Minolta donated the scanner for the purposes of developing the
CAPM system. However, Scenario II will require two scanners (see queuing analysis
under the Labor section of this chapter). Therefore, for Scenario II, one scanner
will have to be purchased when the system is implemented, resulting in an initial
cost of $15,000. The estimated lifetime of the scanners is five years. Based
on this ten-year analysis, replacement costs for the scanners will be incurred
during the fifth year. For the Scenario I, this replacement cost will be $15,000,
while for Scenario II it will be $30,000 since two scanners will have to be
replaced.
Other institutions will have to purchase
both of the initial scanners, as well as a replacement in year five. Therefore,
other institutions will incur an additional $15000 as an initial cost.
Computer Investments: The computer components
of the CAPM system will essentially take advantage of the existing system, so
it is unlikely that an upgrade of either MSELs Horizon system or the network
will be needed. The only computer charges will be for PCs needed for the operation
of the scanners and the robots. The purchase of these computers will be covered
by the CAPM development grants and, therefore, not considered in this analysis.
Maintenance will also be minimal and covered during the normal maintenance performed
on the Horizon system.
The expected lifetime of the computers
is five years. Since this analysis is based on ten years, it will have to include
the lifetime of the computers. The cost of the PCs is $10,000 based on estimates
provided by representatives of MSEL. For the purposes of this analysis, this
covered under the development grants.
The costs for computers at other institutions
are largely dependent on the existing computer network and other facilities
at the place of intended implementation. If the existing system cant support
CAPM, then substantial costs may be incurred in order to upgrade the computer
network. For the purposes of this evaluation, it is assumed that the existing
computer facilities are adequate. Therefore, the only costs in this category
will be for purchasing two PCs to operate the robot and the scanner. Based on
estimates provided by representatives of JHU MSEL, the cost of the PCs is $10,000
each. The expected lifetime for the computers is five years so the cost for
the PCs will be incurred at the inception and during the fifth year.
Book Containers:
The book containers serve two purposes. The motivation for considering
book containers was to facilitate automated retrieval. A preservation librarian
indicated that these containers could also provide preservation benefits with
appropriate materials lining the boxes.
The first type under consideration is
a modification of the current book containers. These are large boxes that will
be used to store multiple books. When CAPM is upgraded to be fully automated
these boxes would still be used, with the addition of the foam spacers as described
above. The second possibility is to use the small cartons, similar to the cartons
that hold VHS videos. In this case, the books will be stored individually in
the cartons, and the cartons will be stored in the larger boxes.
As previously noted, MSEL plans to begin
using the second bay of Moravia Park regardless of whether CAPM is implemented.
Therefore, the larger boxes similar to those used now will be purchased with
or without CAPM and their cost will not be attributed to the CAPM project. Since
CAPM initially will be implemented as a partially automated retrieval system,
only these larger boxes will be required at its inception. When the system is
upgraded, the individual cartons may have to be purchased, depending on which
method for creating the needed spaces is chosen. Since a projected cost for
the foam spacers is not yet available, this analysis will assume that the individual
cartons option will be used and will incorporate the associated cost. The cost
of the individual containers is estimated to be between $1 and $3 each.
Book Container Calculations:
It was mentioned
above that with the planned shelf configuration, the robot would service 432,000
books.. Therefore, 432,000 individual cartons will have to be purchased. This
results in a cost of $432,000 if the cartons are $1 each and $1,296,000 if the
cartons on $3 each. Again, it is assumed that these figures can be generalized
to other institutions.
Setup Costs
If an institution implements CAPM
in shelving facility that already contains a significant amount of books, significant
set up costs will be incurred. These setup costs will be incurred only at the
beginning of the project and include labeling and rearrangement of the books.
In the case of JHU, the second bay of Moravia Park (where CAPM is likely to
implemented) is not yet in use and contains no books. Some books may have already
been shelved in the second bay by the time CAPM is operational. Therefore, set
up costs for JHU will most likely be minimal. To assess the cost associated
with set up, however, the characteristics of the JHU facility (e.g., size, number
of books) and the wage rate at JHU have been utilized. As with other cost categories,
these values to are likely to be different at other institutions. However, the
numbers determined for JHU should be representative of the costs faced by other institutions.
Set Up Calculations
A range of values is determined
using an estimated number of minutes associated with the work to be performed
on each book and a wage rate. The labor rate is based on a medium level Johns
Hopkins University Grade 35 employee. Benefits are not included because it is
assumed that temporary employees will perform these tasks.
| Books | 432,000 | 432,000 |
| Minutes/Book | 3 | 5 |
| Total Time (hours) | 21,600 | 36,000 |
| Hourly Wage | $12.00 | $12.00 |
| Labor Costs | $259,200 | $432,000 |
3.2 Operating Costs
Labor: Labor costs fall under the category of operation and maintenance and
will be incurred yearly. Although labor costs will differ between institutions,
salaries at JHU will be used for this analysis. At JHU, each job is assigned
a grade level. For each grade, there are three salary levels that may be applied
to a position. The salary level depends on the experience and length of service
attained by the individual filling the position. The following table provides
values for the salary levels for grades 32, 33, 35, 36, and 38. To find the
hourly rate, the salary can be divided by 1,950 hours/year.
| Low | Medium | High | |
| Grade 32 | 13,413 | ||
| Grade 33 | 15,043 | ||
| Grade 35 | 18,534 | 22,705 | 26,876 |
| Grade 36 | 20,788 | 25,465 | 30,141 |
| Grade 38 | 25,623 | 32,029 | 38,434 |
For the purposes of this investigation, the benefit rate will be included in the labor costs. The full time benefit rate is 28.5%.
The current employees at Moravia Park are classified as the following grades: catalogergrade 35, Moravia Park staffgrade 36, Moravia Park supervisorgrade 38. With the partially automated scenario, a person will be needed to fill the page-turner position. It is anticipated that the position will be classified as a low level Grade 32 or Grade 33.
Scenario I: It is assumed that the implementation of CAPM will increase the demand for books at Moravia Park. The increased demand may not be noticed immediately. However, awareness of the existence of CAPM will spread with time and it is likely that use will increase as the number of people aware of CAPM rises. Additionally, since MSEL maintains a zero growth policy for housing books onsite, a greater number of books will be shelved at Moravia Park in order to keep up with current acquisitions. With a greater number of books shelved at Moravia Park, the probability increases that library patrons will require the books shelved off-site.. Assuming demand for CAPM grows, it is likely that labor costs will increase with the addition of CAPM. Currently, Moravia Park carries 4.5 full-time positions. Two full time (Grade 38 and Grade 36) individuals and one part time (Grade 36) individual work at Moravia Park. Two cataloguers (Grade 35) are also employed for Moravia Park-related activities but work at MSEL. An additional three catalogers have been aiding Moravia Park when needed but are not represented in the budget calculations. Since it is sometimes difficult to keep up with the current demand, it is probable that CAPM will result in the need for more full time cataloger. Also, depending on the demand for CAPM, it is possible that more staff will be needed at Moravia Park to keep up with cataloging and physical requests. This can be accomplished by upgrading the part time position to a full time position. Therefore, it is estimated here that for a fully automated CAPM, an increase of 1 grade 35 cataloger and 0.5 grade 36 Moravia Park staff person will be needed.
Scenario II: The same increases in demand are estimated for a partially automated CAPM as for a fully automated CAPM. Thus the labor increases detailed in the previous scenario apply to Scenario II as well. Without an automated page-turner, there will be additional labor needs since library employees (grade 32) will have to perform the scanning. Using work-study students is not a viable option for the library due to liability issues. To meet anticipated demand, 2 grade 32 employees will have to be hired to do the scanning for the CAPM system (see queuing analysis below). Relying on manual scanning also means that CAPM will only be available during normal business hours (i.e., approximately 8 a.m. to 4 p.m.).
| Grade | Grade Level | No. Positions | Salary | Salary + Benefits | Total($/year) | |
| Automated CAPM | Grade 35 | Mid | 1 | $22,705 | $29,176 | $46,000 |
| Grade 36 | Mid | 0.5 | $25,465 | $32,722 | $$46,000 | |
| No Page Turner CAPM | Grade 32 | Low | 2 | $13,413 | $17,235 | $80,000 |
| Grade 35 | Mid | 1 | $22,705 | $29,176 | $80,000 | |
| Grade 36 | Mid | 0.5 | $25,465 | $32,722 | $80,000 |
As mentioned above, CAPM will initially operate as a partially automated system. It is assumed that the system will be upgraded in year 5. In this case, the labor costs will be $80,000 range for the first 5 years and will be $46,000 for years 6 through 10. If CAPM is not upgraded, the labor costs will be $80,000 throughout the 10 years period.
An important issue relevant to hiring staff for scanning requested books is the ability of the CAPM system to handle anticipated usage rates. Queuing theory (Ury, 1991) can be used to determine what levels of usage various configurations of the system can handle. Simple queue calculations rely on two parameters: arrival rate and service rate). The amount of time it will take CAPM to fully process a request will depend on the location in the stacks of the requested item and the length of the document to be scanned and whether the document has been scanned previously. It is estimated that the average processing time will be 10 minutes. Therefore, with two manual scanning stations (i.e., two scanners and two employees), on average CAPM will be able to service 12 requests per hour under Scenario II. Currently, the average request rate for items at Moravia Park is approximately 60 per day. Some of these requests are made after normal business hours. However, for this analysis, it is assumed that all requests will be made during normal business hours, when the partially automated CAPM will be available for use. Therefore, using an 8-hour day, the current level of 60 requests per day translates into 7.5 requests per hour.
The traffic intensity, the ratio of the request rate to the total service rate (i.e., the service rate for each server times the number of servers), can be used to determine if a queue will be stable. Stability refers to whether the service can, on average, keep up with the requests. If service cannot keep up with the requests, a backlog will grow indefinitely. If the traffic intensity is less than one, the queue will be stable. For the current level of requests and with two scanners and two manual page turners, traffic intensity is .625, so the system will be stable. Of course as demand grows, the traffic intensity will approach one and the system will become unstable. It is also important to consider the probability of there being a queue, the average number of people in the queue (when there is one), and the average wait time for a patron in the queue (when there is one). The following table presents these statistics for the CAPM system under some of the expected request rates mentioned in the introduction.
| Rate Request | Service Rate | Total Service Rate >with 2 Servers | Traffic Intensity | Probability of a Queue | Av. Length of Queue | Av. Wait Time >in Queue (hours) | ||
| 7.5 | 6 | 12 | .62 | .48 | .81 | .11 | ||
| 9.4 | 6 | 12 | .78 | .69 | 2.5 | .26 | ||
| 12.5 | 6 | 12 | 1.04 | .98 | 22 | 1.8 | ||
| 7.5 | 7.5 | 15 | .50 | .48 | .81 | .08 | ||
| 9.4 | 7.5 | 15 | .63 | .33 | .33 | .04 | ||
| 12.5 | 7.5 | 15 | .83 | .76 | 3.8 | .30 |
The data in the table indicate that with
an average service time of 10 minutes (i.e.,
= 6 requests per hour), the probability of a queue becomes significant when
the request rate reaches about 75 per day (i.e., 9.4 per hour). If the average
service time is 8 minutes (i.e.,= 6 requests
per hour), the probability of a queue becomes significant as the request rate
approaches 100 per day (i.e., 12.5 per hour). If demand grows to these levels
and the probabilities associated with queuing become significant, it is possible
that there will be a need to hire an additional manual page-turner and purchase
another scanner. However, it is anticipated that demand will not grow to these
levels before CAPM is upgraded to the fully automated system.
Since the robotic page turner is yet
to be developed, it is difficult to determine how it will impact the service
rate of the system. As an upper bound, we can assume that it will not speed
up the system at all and that the average service time will be about 10 minutes.
However, it will enable the system to run about 20 hours per day (the system
will have to come down daily for battery charging and occasional maintenance).
If usage of the system does in fact grow to 100 requests per day (or 5 requests
per hour), a queuing analysis shows that the fully automated system with the
above average service time will be able to handle such growth. Under such conditions,
the traffic intensity would be about .42 and the probability of a queue would
be about .25.
A final issue relates to the labor requirements
of other organizations that might implement CAPM. Labor requirements introduced
by CAPM will differ from one institution to another, as will the salary levels.
Some institutions may have adequate staff to cover the increased cataloging
needs associated with CAPM, while some may not. Demand may also differ resulting
in various labor requirements. Therefore, the labor costs associated with CAPM
may vary widely. In order to generalize the results of this analysis, however,
the same range of labor requirements and costs faced by JHU will be assumed
for other institutions.
Maintenance Costs
Maintenance costs are applicable to the
robot, page-turner, scanner, and computer systems. The JHU Mechanical Engineering
Department, who will develop the page-turner, estimates the maintenance costs
of the page-turner to be equivalent to a medium sized photocopier. Based on
costs of maintenance contracts for a medium sized, medium use photocopier, the
maintenance cost for the page turner is estimated to be $2,500/year. The maintenance
for the robot is anticipated to be equivalent to that of the page-turner. Maintenance
contracts for scanners currently used at JHU cost approximately $4500/year per
scanner. Therefore, this value will be used for the cost of maintenance for
the scanner used in CAPM.
Penalty for Reduced Storage Space:
As discussed in section 2, there are
two options for book storage: Scenario IIa and Scenario IIb. Both options will
result in reduced storage capacity and this must be accounted for in the costs.
Shelf Configuration
The current
method of retrieval in the first bay of Moravia Park is a human operated machine
similar to a forklift. The use of this machine requires large aisles between
the shelves (approximately 46.5 inches) to give the machine proper clearance
for operating and turning. With the current method of retrieval, the boxes of
books are stored two rows deep on the shelves. It was initially assumed that
the robot would not be capable of retrieving books that are stored in the back
row. One way to account for this limitation is to configure the shelves in the
second bay differently from how they are configured in the first bay. One major
difference would be storing the boxes of books one layer deep on the shelves.
This would introduce a significant loss of storage capacity. However, the robot
platform will only require about 36 inches of space between the shelves (as
opposed to the 46.5 inches in the current configuration). This reduced spacing
between the shelves will offset some of the loss of storage capacity due to
shelving books one layer deep.
Currently, a bay in Moravia Park holds
18 shelving units that are approximately 40.5 inches deep, one shelving unit
that is approximately 20.1 inches and another that is estimated to be 22.4 inches.
There are 10 aisles having a width of approximately 46.5 inches. Should it be
decided to configure the second bay differently from the first bay, the space
could be reallocated to incorporate CAPM so that there are 30 shelving units
having a depth of 22.4 inches separated by 15 aisles having a width of 36 inches.
The current bay has 18 rows of double
depth storage and two rows of single depth storage. This is equal to 38 rows
of single depth storage. The bay to accommodate CAPM would have 30 rows of single
depth storage. If the bay were set up to incorporate CAPM, a loss of 8 rows
of single depth storage would occur. This is equivalent to a loss of about 21%
of the current storage capacity. In terms of books, the new arrangement would
accommodate approximately 670,000 books rather than the 850,000 books currently
stored.
The other option for dealing with the
robots retrieval limitations is to configure the storage and shelves as
they are in the first bay (i.e., two layer deep storage and shelves 46.5 inches
apart; see Figure 2). The front rows of storage (those accessible to
the robot) could then be used to store high demand volumes, while the back rows
of storage could be used to store low demand volumes. With the highest demand
volumes stored in front, the robot could be relied upon to fulfill most of the
requests for materials. With the shelves 46.5 inches apart, the current method
of manual retrieval would still be feasible and could be used on the relatively
rare occasion that a low demand item is requested. This configuration will introduce
no loss of storage capacity and therefore no costs in this category. Currently,
MSEL plans to set up the second bay of Moravia Park using this configuration.
It has not yet been decided whether high demand volumes will be shelved in the
front rows of the shelves.
Book Storage: As noted above, the robot in a fully
automated CAPM system will require spaces on each side of every book to extract
the books from the boxes. This will cause a loss of storage capacity that must
be included in the cost analysis. The amount of storage lost will depend on
how the spaces are created. One option (Scenario IIa) is to store the books
in individual cartons, similar to those used for VHS videos. Each carton would
be slightly larger than its book, creating the required spaces. The cartons
would be stored in larger boxes similar to those used now. Another option, Scenario
IIb, is to use only the larger boxes (no cartons) with foam spacers between
each book. Using the cartons will involve a greater loss in storage since each
book will have space on both sides within its carton, essentially doubling
the space between each book. Using the foam spacers will have only the necessary
space between each book (See Figure 3).
Since it is assumed that CAPM will be upgraded in year
5, the following annual costs will be incurred at that time.
Calculations
At this time it is anticipated that
the robot will need either 1/8 inch or 1/4 inch on each side of every book for
it to be able to grab a book and extract it. As stated above, the two options
for creating these spaces will result in different losses of storage capacity.
If individual cartons
are used to create the needed spaces, there will be a space on each side of
every book within a box. If the spaces are 1/8 inch, this is equivalent to 1/4
inch between each book, and 1/8 inch between the end books and the side of the
box. There will be 20 front row shelves accessible to the robot, each being
about 100 feet long and having 15 rows of storage. There will be 18 back row
shelves that will not be accessible to the robot. Without spaces between the
books, the total storage of the second bay of Moravia Park would be approximately
1,026,000 books (540,000 on the front shelves and 486,000 on the back shelves).
With spaces created using the individual cartons, the front shelves will be
able to store approximately 432,000 books for a total storage of 918,000 books
(see appendix 2 for spreadsheet calculations). Therefore, the loss of storage
capacity due to the cartons would be 108,000 books, or 10.5 percent.
This loss of storage capacity can be assigned a dollar
value based on the annual leasing costs for Moravia Park. The lease rate is
$140,000 per year. If the book storage bays account for approximately 80% of
the area in Moravia Park, the approximate cost attributed to book storage is
$112,000. Thus, with 10.5 percent of the capacity lost, an annual cost of $11,800
could be attributed to CAPM.
As mentioned, it is possible that the robot will need
1/4 inch spaces to grab a book. A similar set of calculations can be done to
derive opportunity costs of creating the 1/4 inch spaces using individual cartons.
The 1/4 inch spaces would result in an annual opportunity cost of $19,600.
Foam Spacers Option: If the needed spaces between
books are created using foam spacers and the needed spaces are 1/8 inch in size,
there will be 1/8 inch between each book and between the end books and the side
of the box. Using the same figures as in the calculations for the individual
cartons, it was found that the foam spacers would result in a storage loss of
72,000 books, or 7 percent. Therefore, creating the necessary spaces in this
way will result in a lost storage capacity annual cost of $7,900. If the spaces
needed between the books is 1/4 inch and the foam spacers are used, the annual
opportunity cost would amount to $11,800.
It is difficult to determine how much of a cost for lost
storage capacity would be faced by other institutions. The number depends largely
on the size of the facility, the cost for leasing the facility and the configuration
of the shelves within the facility. However, since a fully automated CAPM will
require spaces between books, every institution using the CAPM system will incur
the associated opportunity cost, i.e., facilities will be able to shelve fewer
books and a cost must be assigned to such losses. For purposes of comparison,
it will be assumed here that other institutions will face costs for lost capacity
similar to those faced by JHU. Though this is not realistic, it is the best
way to ensure that this unavoidable cost is included in the assessed costs for
implementing CAPM at institutions other than JHU.
Variable O&M Costs
Electricity Costs:
Electricity is a cost that will be incurred
on a yearly basis and will vary depending on usage of the system. The components
of CAPM that will require electricity are the robot, the page-turner, and the
scanner.
Robot: The robot receives its
operating power from two batteries that are part of the base of the robot. The
robot is expected to be able to operate for eight hours from fully charged batteries.
No more than one charge per day will be needed to meet anticipated usage rates
of the CAPM system. Being charged once per day, the robot will use approximately
2.2 KWH/day.
Page-Turner: Although it
is still in development, the JHU Mechanical Engineering Department estimates
that the automatic page-turner will use 500 watts of electricity at peak usage
and 50 watts while it is inactive. For anticipated usage rates, it can be estimated
that the page-turner will be at peak usage for no more than 16 hours per day
and will be inactive for the other 8 hours. Therefore, the page-turner will
use about 8.4 KWH/day. The cost of the electricity to run the page-turner will
be incurred starting in year 5.
Scanner:The brochure for
the Minolta DPCS 3000 scanner indicates a peak consumption of 1 kilowatt. It
is expected that the scanner will operate no more than 16 hours per day. This
results in a use of 16 KWH/day. Since two scanners will be used under Scenario
II, 32 KWH/day will be used.
Calculations
Under Scenario II, the robot and
two scanners will result in an increase in electrical usage of 34.2 KWH/day.
Under Scenario I, the robot, page-turner and one scanner will result in an increase
of electrical usage of approximately 26.6 KWH/day. The average electricity rate
paid by JHU over the last 4 years is $0.05225/KWH. This value will be used here.
Under Scenario II, the additional electricity costs will amount to $1.79 per
day, or $652 per year. The increase in electrical usage Scenario I will cost
$1.39 per day, or $507 per year.
It is assumed that these figures for
electricity costs are representative of those that would be incurred by other
institutions. Hence, the same numbers will be used in summing up the costs for
organizations other than JHU.
Total Costs
The total of the annual expenses will
be expressed in present dollars. A specific percent was added to the annual
expenses to account for salary increases and inflation. A value of present worth
expresses the total flow of future expenditures as a one-time expenditure at
the end of year zero.The following tables depict the estimates
of the present worth of the total cost of CAPM for JHU and for other institutions
| JHU | ||
| Present Worth | Fully Automated CAPM | Partially Automated CAPM |
| Low | $1,319,000 | $1,405,000 |
| High | $2,449,000 | $2,442,000 |
| Other Institutions | ||
| Present Worth | Fully Automated CAPM | Partially Automated CAPM |
| Low | $1,435,000 | $1,516,000 |
| High | $2,660,000 | $2,603,000 |
It is also useful to examine how much fixed and variable costs contribute to the total costs. The tables below provide information on the fixed and variable components of the costs.
| JHU | |||
| Category | Fully Automated CAPM | Partially Automated CAPM | |
| Low | Fixed | $710,000 | $721,000 |
| Variable | $548,000 | $684,000 | |
| High | Fixed | $1,747,000 | $1,758,000 |
| Variable | $703,000 | $684,000 |
| Other Institutions | |||
| Category | Fully Automated CAPM | Partially Automated CAPM | |
| Low | Fixed | $826,00 | $832,000 |
| Variable | $609,000 | $684,000 | |
| High | Fixed | $1,958,000 | $1,919,000 |
| Variable | $702,000 | $684,000 |
Cost Per Use
An initial estimate of the expected usage will be determined by the user survey. However, for the purposes of this evaluation, a range of usage values will be provided. As a reference, the current number of daily requests for books and articles from Moravia Park is approximately 50. Using a range of values centered at this current average, estimates of cost per use can be determined. These numbers provide a more realistic presentation of the costs that can easily be compared to the willingness-to-pay data gathered in the user survey.
Based on the total costs, values of cost per use were calculated and are presented in the following tables. A 5% increase in annual usage was estimated to account for user familiarity with CAPM.
| JHU | Usage/Day | Cost/Use | |
| Fully Automated CAPM | 100 | Low | $3.81 |
| High | $7.07 | ||
| 75 | Low | $5.07 | |
| High | $9.42 | ||
| 50 | Low | $7.61 | |
| High | $14.13 | ||
| 30 | Low | $12.69 | |
| High | $23.56 | ||
| 20 | Low | $19.03 | |
| High | $35.33 | ||
| No Page Turner CAPM | 100 | Low | $4.05 |
| High | $7.05 | ||
| 75 | Low | $5.40 | |
| High | $9.39 | ||
| 50 | Low | $8.11 | |
| High | $14.09 | ||
| 30 | Low | $13.51 | |
| High | $23.48 | ||
| 20 | Low | $20.27 | |
| High | $35.23 |
| Other Institutions | Usage/Day | Cost/Use | |
| Fully Automated CAPM | 100 | Low | $4.22 |
| High | $7.68 | ||
| 75 | Low | $5.62 | |
| High | $10.23 | ||
| 50 | Low | $8.43 | |
| High | $15.35 | ||
| 30 | Low | $14.05 | |
| High | $25.59 | ||
| 20 | Low | $21.08 | |
| High | $38.38 | ||
| No Page Turner CAPM | 100 | Low | $4.37 |
| High | $7.51 | ||
| 75 | Low | $5.83 | |
| High | $10.01 | ||
| 50 | Low | $8.75 | |
| High | $15.02 | ||
| 30 | Low | $14.58 | |
| High | $25.03 | ||
| 20 | Low | $21.87 | |
| High | $37.55 |
The above tables present cost per use data based on the total costs for the CAPM system. It is also useful to examine cost per use data calculated using only the O&M costs. As assessed in this chapter, the only differences between the general case and the case for JHU are initial investment costs (e.g., the robot, scanner etc.). As mentioned, the O&M costs will vary across institutions. For this chapter, however, the O&M figures determined for JHU are considered to be representative of those likely to be encountered at other institutions. Therefore, the O&M costs are the same for both cases and the following table is valid for both JHU and the general case. Furthermore, the O&M costs in Scenario II were not represented by ranges. Hence, there is only one cost per use value for each usage level in Scenario II.
| Usage/Day | Cost/Use | ||
| Automated CAPM | 100 | Low | $1.76 |
| High | $2.03 | ||
| 75 | Low | $2.34 | |
| High | $2.70 | ||
| 50 | Low | $3.51 | |
| High | $4.05 | ||
| 30 | Low | $5.86 | |
| High | $6.76 | ||
| 20 | Low | $8.79 | |
| High | $10.13 | ||
| No Page Turner CAPM | 100 | $1.97 | |
| 75 | $2.63 | ||
| 50 | $3.95 | ||
| 30 | $6.58 | ||
| 20 | $9.87 |
If one is unfamiliar with costs of library services, some of these values may seem high. However, many of these cost per use values are not unlike the costs of another commonly used library service, interlibrary loan (ILL). The following table summarizes the mean cost to libraries for providing ILL. These values are based on a 1998 study of North American college and research libraries (Jackson, 1998).
| Mean Cost | Research University Libraries | College Libraries |
| Borrowing Unit Cost | $18.35 | $12.08 |
| Lending Unit Cost | $9.48 | 7.25 |
| Combined Unit Cost | $27.83 | $19.33 |
Comparing the cost per use data for CAPM and the average ILL costs one can see that under most scenarios CAPM costs less than ILL. In fact, only if the use of CAPM is very low (indeed, much lower than is expected) do the cost per use numbers based on the total costs begin to exceed the costs for ILL. The cost per use for CAPM based only on the O&M costs are much lower than ILL for all usage levels analyzed. This is not to suggest that the CAPM system can replace ILL and offer cost savingsthe systems provide different services and are not necessarily substitutes. The comparison is made to show that the costs for CAPM are less than another widely used library service.
Risk
This risk analysis is designed to look at the costs associated with the implementation of CAPM that would be recoverable if the system does not function as expected. It is important to differentiate the sunk costs from those that can be avoided should a decision be made to terminate the CAPM program before the lifetime assumed in the previous sections. Other studies have shown that many projects do not make careful studies of risk. A survey of 200 British companies showed that for projects having budgets greater than 660,000 pounds, 90 percent were over budget, 98 percent had changed specification, 60 percent were over time, and 20 percent were inappropriate (Willcocks and Griffiths, 1994). In the instance of CAPM, the demand and benefits will be projected based on a user survey conducted during the fall of 2000. The costs are being assessed through this analysis. Technological feasibility is not expected to be a problem.
If CAPM is implemented and the demand projected by the survey does not materialize then CAPM may be discontinued. It is unlikely that the much of the money invested in the project could be recovered. The robot and the page-turner (if it is already implemented) are sunk costs. The amount of money that could be obtained for selling the robots would be minimal compared to the cost required to produce them. Expenditures on the book cartons (those used to create the spaces between the books) are also sunk costs. Although, the cartons would not have to be removed, they would serve little purpose without the CAPM system. Additionally, funds spent on book set-up are not recoverable.
If CAPM is terminated after it is upgraded to a fully automated system, the spaces between the books needed by the robot will present a problem. As discussed, these spaces result in a loss of storage capacity with an annual cost on the order of $10,000. If the CAPM system is removed MSEL either will have to invest time and resources to remove the spaces, or it will have to absorb the annual costs associated with the loss of storage. At this time, it is difficult to determine which option would be economically optimal. Some pertinent factors in such a decision would be the existing rate of acquisitions and the rate at which the second bay of Moravia Park is being filled. Clearly this aspect of the project does present some risk.
If CAPM is terminated after five years of service, funds allocated to replacement PCs and a replacement scanner (recall that these items are expected to be replaced in year 5) likely are recoverable costs. These components could easily be used in other contexts, and although there would be some costs associated with transferring them, the cost would be minimal compared to the value of the machines.
Conclusion
In the face of increasing pressures on storage space and decreasing budgets, libraries are forced to consider new means for managing their expanding collections. Off-site shelving has emerged a cost-effective way to meet this challenge. However, off-site shelving results in decreased ability to browse. It is hoped that CAPM can remedy this problem by speeding access to materials stored off-site and by opening off-site collections to patron browsing.
This chapter has summarized the costs involved in implementing the CAPM system. The most important result of this analysis is that the costs per use for CAPM are likely to be comparable to or less than that for ILL. Although CAPM requires significantly more initial investment than ILL, the comparison of the two shows that, in the long run, the costs for CAPM are within a range that is reasonable for most libraries. Furthermore, this result warrants that any decisions about CAPM be based on the comparisons of these cost per use values with anticipated patron benefits.
In conclusion, Leblanc (1995, p. 301) quotes Thomas Mann as saying "to spend enormous amounts of money assembling book collections and then to make access to them only superficial, partial, incomplete, and haphazard is to throw money away rather than to use it prudently." In many cases, CAPM might represent a prudent use of library funds.
References
Baker, Sharon L., Wilfred E. Lancaster. 1977. The Measurement and Evaluation of Library Services. 2nd Edition. Information Resources Press.
Blagden, John. 1980. Do We Really Need Libraries? Clive Bingley Ltd. Publishing. New York.
Boss, Richard W. 1993. Automated Storage and Retrieval: A Viable Option. Library Systems. 13(12): 91-93.
Choudhury, Sayeed. 1998. A Proposal for Comprehensive Access to Off-Site Library Print Materials. Submitted to The Andrew W. Mellon Foundation by Milton S. Eisenhower Library, The Johns Hopkins University, 11 May.
Cox, John E. 1998. "The Changing Economic Model of Scholarly Publishing: Uncertainty, Complexity, and Multimedia Serials." Library Acquisitions: Practice and Theory. 22(2):161-166.
Emery, Charles D. 1993. "Buyers and Borrowers; The Application of Consumer Theory to the Study of Library Use. The Haworth Press. New York. pp. 1-175.
Gabriel, Mike and Mitchell Flesner. 1990. "Surprising Responses on the Issue of Convenience of Use: A User Survey of Microforms in One Academic Library. Microform Review. 19(2):69-72.
Getz, Malcolm. 1991. "The Electronic Library: Analysis and Decentralization in Collection Decisions." Journal of Library Administration. 14(3):71-84.
Getz, Malcolm. 1988. "Increasing the Value of User Time." The Bottom Line. 1(2):37-39.
Jackson, Mary E. 1998. "Measuring the Performance of Interlibrary Loan Operations in North American Research & College Libraries." Association of Research Libraries. Washington D.C.
Kantor, Paul B., Tefko Saracevic, Joann D�Esposito-Wachtmann. 1995a. "Studying the Cost and Value of Library Services-Final Report." Alexandria Project Laboratory. School of Communication Information and Library Studies, Rutgers, the State University of New Jersey. Technical Report APLAB/94-3/1,2,3,4.
Kantor, Paul B. 1995b. "What Bang for the Buck: Costs and Beneficial Impacts of Library Operations" in The Economics of Information in the 1990s. ed. Jana Varlejs. Jefferson, North Carolina. pp. 15-23.
King, Donald W. and Jose-Marie Griffiths. 1995. "Economic Issues Concerning Electronic Publishing and Distribution of Scholarly Articles." Library Trends. 43(4):713-740.
Kingma, Bruce. 1996."The Value of Time" in The Economics of Information: A Guide to Economic and Cost-Benefit Analysis for Information Professionals. Libraries Unlimited, Inc. Englewood, Colorado. pp.139-152.
LeBlanc, Jim. 1995. "Classification and Shelflisting as Value Added: Some Remarks on the Relative Worth and Price of Predictability, Serendipity, and Depth of Access." LRTS 39(3):294-302.
Rowell, Christine A. 1996. "On Campus: Moravia Park Continues to Ease Space Crunch." The Gazette: The Newspaper of the Johns Hopkins University. 2 December.
Willcocks, Leslie and Catherine Griffiths. 1994. "Predicting Risk of Failure in Large-Scale Information Technology Projects." Technological Forecasting and Social Change, 47:205-228.